CHAPTER 8. OPENING DATE TARGET

Back from Easter holidays, and back to work. Acording to the Shopping Center contract conditions, the limit date to opening is June 30th , but I expect to be open before that date. It depends basically in how much time could need the Xunta Tourism Department to approve the file and finish all the paperwork. Theoretically, they say that the whole process usualy takes 45 days, so thinking in a two months gap would be realistic. Getting all the documents ready and registered at the Xunta Office in April’s first week, and taking into account that there are two long weekends in May, the first estimated target date should be June 10th.

Notice that at the bottom of this page there is a link, “Subscribe to: Posts”, wich allows you to receive in your “Favoritos-Fuentes” Internet Explorer folder the new posts in the blog, usually once a week. It’s useful because if you are interested in this project, you don’t need to guess when a new post should be placed, you will always get the the latest version.